Agreement Date
14th July 2015
Completion
 13th March 2020

Contractor                          SHARMA – LAMA – SWACHHANDA   JV

Employer                             Bridge Project Eastern Sector NO: 1

Contract                               Design and Build of Mawa River Bridge (Damak) , Jhapa

Agreement                          14th July 2015

Completion                         13th March 2020

Work Value                         NPR 30,22,91,750